Main Street Project Update, February 14, 2025

Construction Update

Sewer main construction on Main St. between Church St. and
S. Winooski will continue.

Work on underground utilities within the Main/S. Winooski intersection will continue throughout the month of February.

Water main replacement and temporary water main work will continue through February.

Please see the parking and traffic sections below for more information on impacts.

NEARBY PROJECT INFORMATION

CHAMPLAIN PARKWAY:

As construction on the next phase of the Parkway project nears, please visit http://champlainparkway.com/
for more information on construction timelines, traffic impacts and more.

Click HERE to sign up to receive project updates.

Traffic Update

Which streets are closed?

Main St is closed from Church St through the S. Winooski Ave intersection

Main and Church intersection is open to vehicles.

Timeframes for closures are subject to change. Updates will be provided as frequently as possible. Your understanding and patience are appreciated.

See the map below for street and parking accessibility, construction work locations and detours.

Parking Update

Where can I park?

On street parking is available except where a meter bag or ‘No Parking’ sign is present.

Available Lots/Garages:
Courthouse Plaza Garage, S. Winooski Ave entrance, city rates ($1.50/hr)

Main/Winooski lot accessed via S .Winooski Ave.
Lower portion only

Parking restrictions:

On-street parking along Main St: Church – S. Winooski Ave.

On-street parking along S. Union and College St.

Main: St Paul – Church northern parking lane/sidewalk closure

Explore the City of Burlington’s interactive parking map.

Nearby Project Alerts

For information on nearby projects, click below to go to the
DPW Construction Portal

For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/

Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts

Download Resources For Your Business!

Communicate to your current and potential customers/patrons that you are open for business and give them access to more information during construction.
Learn More
GoUp

Don't Miss The Latest!

Update March 21, 2025

The MainS. Winooski intersection is scheduled to reopen to North/South through traffic by the end of the day Monday, 3/24.