Main Street Project Updates Feb 2, 2024

Construction Update

 Work on Main Street is scheduled to begin on Monday, 2/5 between the intersections of South Winooski and South Union.

Main Street will be closed to all non-local traffic on this block for a minimum of two weeks. The contractor will begin excavation for, and installation of new sewer infrastructure.

Traffic Update

Main Street will be closed to all non-local traffic on this block for a minimum of two weeks. Restoration of east-bound traffic is anticipated during the third and fourth week of work, and full restoration of two-way traffic is anticipated after four weeks.  

The sidewalk on the southern side of Main Street will be open entirely, with sections on the north side being closed throughout certain portions of work. Pedestrian detours will be in place for any impacts to the sidewalk.

Parking Update

The public parking lot at the northeast corner of Main Street and S. Winooski will be closed until further notice.

Download Resources For Your Business!

Communicate to your current and potential customers/patrons that you are open for business and give them access to more information during construction.
Learn More
GoUp

Don't Miss The Latest!

Update November 15, 2024

The intersection of Main/St. Paul Street remains closed. Construction of the new permanent water main between Pine and Church is