Main Street Project Updates October 11, 2024

Construction Update

Sewer work in the intersection of Church and Main will continue.

Restoration of the roadway on lower Church Street between King Street to just south of Main Street will continue next week.

Permanent line striping and roadway marking on Church St between King and Maple is scheduled for early next week. This work is weather-dependent.

Temporary waterline work will continue along Main Street between Pine and Church.

Please see the parking and traffic sections below for more information on impacts.

Traffic Update

The intersection of Main and Pine will close early/mid week next week and remain closed for 3-4 weeks.

The Main and Church intersection is closed.

Church Street from King to Main Street remains closed.

Flagged traffic will be required on Church St. between Maple and King for
painting operations.

  Pedestrian traffic will be maintained around work zones. Follow designated pedestrian signage.

See the map below for construction work locations and detours.

For more information on current construction work locations,  detour, and pedestrian impacts for multiple DPW large construction project impacts within the City, click on the map image below.

Parking Update

Additional public parking is available at the Courthouse Plaza garage

Parking at the Courthouse Plaza Garage (South Winooski Ave. entrance only) continues to be available at the City rate of $1.50/hour and space is still highly available.

City rates are only available on the level that is accessed from the South Winooski Ave. entrance.

Public parking on the surface level (access from Church Street) is available nights/weekends and is managed by Unified Parking Partners and follows
their rate structure.

Some public parking has been restored on the lot located at the corner of Main St.
and S. Winooski Ave.

Parking directly in and adjacent to work zones will be impacted, please obey on street parking signage.

There will be no parking on the Flynn (south) side of Main St. between St. Paul Street and S. Winooski Ave.  

Limited on-street parking exists on Main Street between St Paul and S Winooski. Please do not park in areas that have meter bags or are coned off.

Please follow signage for access to local businesses and alternate business parking.
Explore the City of Burlington’s interactive parking map.

Nearby Project Alerts

Church Street Marketplace Construction 
Starting Monday, October 14 work will begin to repair and replace the Globe on the Church Street Marketplace between Main and College streets.
This work is anticipated to take 3 – 4 weeks. 

For information on nearby projects, click below to go to the
DPW Construction Portal

For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/

Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts

Download Resources For Your Business!

Communicate to your current and potential customers/patrons that you are open for business and give them access to more information during construction.
Learn More
GoUp

Don't Miss The Latest!

Latest Update – October 15, 2024

The intersection of Pine and Main is scheduled to close on 10/16/24. The intersection of Main and Church will remain