Construction Update
Sewer work in the intersection of Church and Main will continue.
Line striping and roadway marking on Church St between King and Maple is scheduled to occur in the next several weeks and will be completed before winter weather sets in.
Permanent waterline work has begun along Main Street between Pine and Church.
Please see the parking and traffic sections below for more information on impacts.
Traffic Update
The intersection of Main and Pine is now closed.
The Main and Church intersection is closed.
Church Street from King to Main Street remains closed.
Pedestrian traffic will be maintained around work zones. Follow designated pedestrian signage.
See the map below for construction work locations and detours.
For more information on current construction work locations,
detour, and pedestrian impacts for multiple DPW large construction project impacts within the City, click on the map image below.
Parking Update
Additional public parking is available at the Courthouse Plaza garage
Parking at the Courthouse Plaza Garage (South Winooski Ave. entrance only) continues to be available at the City rate of $1.50/hour and space is still highly available.
City rates are only available on the level that is accessed from the South Winooski Ave. entrance.
Public parking on the surface level (access from Church Street) is available nights/weekends and is managed by Unified Parking Partners and follows
their rate structure.
Some public parking has been restored on the lot located at the corner of Main St.
and S. Winooski Ave.
Parking directly in and adjacent to work zones will be impacted, please obey on street parking signage.
There will be no parking on the Flynn (south) side of Main St. between St. Paul Street and S. Winooski Ave.
Limited on-street parking exists on Main Street between St Paul and S Winooski. Please do not park in areas that have meter bags or are coned off.
Please follow signage for access to local businesses and alternate business parking.
Explore the City of Burlington’s interactive parking map.
Nearby Project Alerts
Church Street Marketplace Construction
Work to repair and replace the Globe on the Church Street Marketplace between Main and College streets is underway. This work is anticipated to take 3 – 4 weeks.
For information on nearby projects, click below to go to the
DPW Construction Portal
For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/
Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts