Construction Update
Sewer main construction on Main St. between Church St. and
S. Winooski will continue.
Water main replacement and temporary water main work will continue through January.
Holiday schedule:
Next week the contractor will not be working Tuesday or Wednesday, 12/24-12/25. Work will resume on Thursday, 12/26.
The following week the contractor will not be working from noon on Tuesday, 12/31 through Wednesday, 1/1/25. Work will resume on Thursday, 1/2
The next weekly update will be issued on Friday, 1/3.
Overall, the contractor will work to reduce the construction limits during the holidays to the greatest extent possible.
Please see the parking and traffic sections below for more information on impacts
Traffic Update
Main Street and Winooski Ave. Intersection:
Westbound Main Street traffic will be accommodated for passenger vehicles up to Winooski Avenue 24/7 with the ability to turn northbound and southbound onto Winooski Avenue through December 29th.
Flaggers will be onsite to assist with traffic control as needed.
The intersection of Main and S. Winooski Avenue is scheduled to fully close as early as Monday, 12/30/24.
Isolated closures will occur on Pine St., and along Main Street
between Pine and Church St.
The Main/Church intersection will remain closed to vehicular traffic. Pedestrian access at this location has been expanded.
The St. Paul/Main Street intersection remains closed to vehicular traffic until the week of 12/30 when single lane traffic is anticipated to begin.
Deliveries into the intersection will be accommodated throughout. Traffic control personnel will be onsite to assist delivery vehicle access.
All vehicular access on Main Street between St. Paul and S. Winooski is restricted.
See the map below for construction work
locations and detours.
For more information on current construction work locations,
detour, and pedestrian impacts for multiple DPW large construction project impacts within the City, click on the map image below.
Map of current work:
Parking Update
Additional public parking is available at the Courthouse Plaza garage
All downtown core parking meters will have a holiday price roll-back to 99 cents / hour from Thanksgiving through New Year’s.
Reduced parking is available on Main Street between Pine and St. Paul Street. No parking is available on Main between St. Paul and S. Winooski Ave.
Parking directly north/south of the active work zone at the St. Paul Street intersection will be impacted.
Parking at the Courthouse Plaza Garage (South Winooski Ave. entrance only) continues to be available at the City rate of $1.50/hour and space is still highly available.
Some public parking has been restored on the lot located at the corner of Main St. and S. Winooski Ave.
Parking directly in and adjacent to work zones will be impacted,
please obey on-street parking signage.
Please do not park in areas that have meter bags or are
coned off.
Please follow signage for access to local businesses and alternate business parking. Click below to access and explore the City of Burlington’s interactive parking map.
Nearby Project Alerts
For information on nearby projects, click below to go to the
DPW Construction Portal
For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/
Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts