Main Street Project Update, January 31, 2025
Construction Update
Sewer main construction on Main St. between Church St. and
S. Winooski will continue.
Work on underground utilities within the Main/S. Winooski intersection will continue throughout the month of February.
Water main replacement and temporary water main work will continue through February.
Please see the parking and traffic sections below for more information on impacts.
Traffic Update
Which streets are closed?
Main St is closed from Church St through the S. Winooski Ave intersection (anticipated through Feb. 2025)
The intersection of Main/Church will experience a brief closure
next week.
Beginning as early as 2/10 Main Streeet: St Paul to Church will close to vehicle traffic for a few weeks.
Timeframes for closures are subject to change. Updates will be provided as frequently as possible.
Your understanding and patience are appreciated.
See the map below for street and parking accessibility, construction work locations a
Parking Update
Where can I park?
On street parking is available except where a meter bag or ‘No Parking’
sign is present.
Available Lots/Garages:
Courthouse Plaza Garage, S. Winooski Ave entrance, city rates ($1.50/hr)
Public lot located at the northeast corner of Main St and S. Winooski Ave (accessible from Main St).
Parking restrictions:
On-street parking along Main St: Church – S. Winooski Ave.
On-street parking along S. Union and College St.
Main Street: St Paul to Church northern parking lane/sidewalk closure
Nearby Project Alerts
For information on nearby projects, click below to go to the
DPW Construction Portal
For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/
Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts