Main Street Project Update, March 14, 2025

Construction Update

Work on underground utilities within the Main/S. Winooski intersection will continue throughout the month of February.

Sewer main construction is progressing east (uphill) from the Main/S. Winooski intersection toward S. Union.

Work is finishing up on the underground stormwater tanks located in front of City Hall Park. Work on the underground stormwater tank located near the Pine and Main intersection has begun.

Water main replacement and temporary water main work will continue through February.

Please see the parking and traffic sections below for more information on impacts.

NEARBY PROJECT INFORMATION

CHAMPLAIN PARKWAY:

As construction on the next phase of the Parkway project nears, please visit http://champlainparkway.com/
for more information on construction timelines, traffic impacts and more.

Click HERE to sign up to receive project updates.

Traffic Update

Which streets are closed?

Main St is closed from Church St. through the S. Winooski Ave intersection.

Main/Church intersection is open to vehicles.

Main St: St. Paul to Church is reduced to one lane of travel (eastbound). Parking may be impacted at times

Timeframes for closures are subject to change. Updates will be provided as frequently as possible. Your understanding and patience are appreciated.

See the map below for street and parking accessibility, construction work locations and detours.

Parking Update

Where can I park?

On street parking is available except where a meter bag or
‘No Parking’ sign is present.

Available Lots/Garages:

Courthouse Plaza Garage, S. Winooski Ave entrance, city rates ($1.50/hr)

Main/Winooski lot accessed via S .Winooski Ave.
Lower portion only.

On-Street Parking restrictions:

S. Union and College St.

Main St: St Paul – Church: Northern parking lane/
sidewalk closure. Parking on the south side of Main St. may be impacted
at times.

Main St: Pine to St. Paul: Limited on-street parking on the North side of
the street.

MAIN STREET PARKING

Main St: Church – S. Winooski: some parking on the western section of the road has been restored.
(see image below)

Explore the City of Burlington’s interactive parking map.

Nearby Project Alerts

For information on nearby projects, click below to go to the
DPW Construction Portal

For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/

Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts

Download Resources For Your Business!

Communicate to your current and potential customers/patrons that you are open for business and give them access to more information during construction.
Learn More
GoUp

Don't Miss The Latest!

Latest Update – March 27, 2025

S.Winooski Ave is open to North/South through traffic. The Main/S. Union intersection closed except right hand (eastbound) turns from S. Union