Work continues along Main Street between S. Winooski Ave and S. Union Street. Water service interruptions are scheduled on 2/25 for some properties on this block.
The intersection of Pine/Main has been reopened. The intersection of Main/St. Paul is now closed. The Main/Church intersection will remain closed for several weeks.
Temporary waterline work at the Pine and Main Street intersection is scheduled to begin on Monday, 9/16. The intersection of Church and Main Street will remain closed for several weeks while sewer work continues. A widening of the sidewalk on the north side of Main St between Church and S.
Temporary waterline work within the St. Paul and Main Street intersection is scheduled for completion next week. The intersection of Church and Main Street will remain closed for several weeks while sewer work continues. A widening of the sidewalk on the north side of Main St between Church and S.
The intersection of Church and Main Street will remain closed for several weeks while sewer work continues. Temporary waterline work within the St. Paul and Main Street intersection will continue next week. Water valve work continues in the intersection of Main and Pine. In observance of the Labor Day holiday
Sewer work continues north along Church St. toward Main St. and has progressed into the intersection of Church and Main, and the intersection is now closed. Church St. from King to Main remains closed. Water valve work continues in the intersection of Main and Pine. In observance of the Labor
Sidewalk and curb work on King St. from S. Winooski Ave. through the intersection of Church St. has been completed. Paving along this block of King St. is scheduled for this weekend. Sewer work continues north along Church toward Main Street. This work will progress into the intersection of Church
Sidewalk and curb work on King Street between S. Winooski Ave. through the intersection of Church St. is scheduled for completion this week. Sewer work continues to progress north along Church St. toward Main St. Water work will start with the installation of valves in the intersections of Main/Pine and
Sidewalk and curb work on King Street between S. Winooski Ave. through the intersection of Church St. continues. Sewer work is also progressing north along Church Street toward Main Street. A lane shift continues to be in place on Main Street between Pine Street and S. Champlain Street. Both directions
Water work will start on Main Street Monday morning between Pine Street and S. Champlain Street and will last through the week. A lane shift will allow traffic to be maintained in each direction along Main. The intersection of S. Winooski Ave and King Street will be open with lane
The intersection of S. Winooski Ave. and King Street has been reopened. Sewer work along King Street has progressed to the intersection of King and S. Winooski Ave. Additional parking has been opened at the lot located at the corner of Main St. and S. Winooski Ave. Excavation along Church
The intersection of S. Winooski Ave. and King Street will be closed until early next week. Sewer work along King Street has progressed to the intersection of King and S. Winooski Ave. Additional parking has been opened at the lot located at the corner of Main St. and S. Winooski