Main Street Project Updates August 16, 2024

Construction Update

Paving of King Street from Church Street to S. Winooski Avenue is scheduled for Friday, 8/16 and Saturday, 8/17.

Sewer work continues north along Church Street
toward Main Street. This work will progress into the intersection of Church and Main on Monday, 8/19.

The installation of water valves in the intersections of Main/Pine and Main/St Paul will continue. No water outages are anticipated at this time.

Please see the parking and traffic sections below for more information on impacts.

Traffic Update

Roadway/Intersection Reopenings:

King Street between Church Street and S. Winooski Ave will reopen on Monday, 8/19.

The King/Church intersection will reopen Monday, 8/19.

Roadway/Intersection Closures:

The intersection of Main and Pine Street will be closed beginning
Monday, 8/19.

Main and Church intersection is scheduled to close Monday, 8/19.

 Church Street from King to Main Street remains closed.

Pedestrian traffic will be maintained around work zones. Follow designated pedestrian signage.

Parking Update

Additional public parking is available at the Courthouse Plaza garage

Parking at the Courthouse Plaza Garage (South Winooski Ave. entrance only) continues to be available at the City rate of $1.50/hour and space is still highly available.

City rates are only available on the level that is accessed from the South Winooski Ave. entrance.

Public parking on the surface level (access from Church Street) is available nights/weekends and is managed by Unified Parking Partners and follows
their rate structure.

Some public parking has been restored on the lot located at the corner of
Main St. and S. Winooski Ave.

Parking directly in and adjacent to work zones will be impacted.

Please follow signage for access to local businesses and alternate business parking.
Explore the City of Burlington’s interactive parking map.

Nearby Project Alerts

Church Street brick work will continue at the intersection of Church and College Street. There will be no through traffic between South Winooski and St. Paul Street along College Street (although access to Center Street will be maintained).
On-street parking will still be available

For information on nearby projects, click below to go to the

DPW Construction Portal

For information on the Champlain Parkway and traffic impacts, click below

http://champlainparkway.com/

Sign up for VT-Alert to receive major alerts about work in Burlington

Sign up for VT Alerts

Download Resources For Your Business!

Communicate to your current and potential customers/patrons that you are open for business and give them access to more information during construction.
Learn More
GoUp

Don't Miss The Latest!

Update November 15, 2024

The intersection of Main/St. Paul Street remains closed. Construction of the new permanent water main between Pine and Church is