Main Street Project Update, January 10, 2025

Construction Update

Sewer main construction on Main St. between Church St. and
S. Winooski will continue.

Water work at Main and St. Paul will be completed by the end of the day today.

Water main replacement and temporary water main work will continue through January.

Please see the parking and traffic sections below for more information on impacts.

Traffic Update

The intersection of Main and S. Winooski Avenue is fully closed.

All vehicular access on Main Street between Church and S. Winooski is restricted.

See the map below for construction work
locations and detours.

For more information on current construction work locations, detour, and pedestrian impacts for multiple DPW large construction project impacts within the City, click on the map image below.

Parking Update

Additional public parking is available at the Courthouse Plaza garage

There is no available parking on Main St. between Church and S. Winooski Ave.

Parking along S. Union and College St. has been restricted to allow for emergency access while Main/Winooski intersection is closed.

Parking at the Courthouse Plaza Garage (South Winooski Ave. entrance only) continues to be available at the City rate of $1.50/hour and space is still highly available.

Some public parking has been restored on the lot located at the corner of Main St. and S. Winooski Ave.

Parking directly in and adjacent to work zones will
be impacted,
please obey on-street parking signage.

Please do not park in areas that have meter bags or are
coned off.

Please follow signage for access to local businesses and alternate business parking. Click below to access and explore the City of Burlington’s interactive parking map.

Explore the City of Burlington’s interactive parking map.

Nearby Project Alerts

For information on nearby projects, click below to go to the
DPW Construction Portal

For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/

Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts

Download Resources For Your Business!

Communicate to your current and potential customers/patrons that you are open for business and give them access to more information during construction.
Learn More
GoUp

Don't Miss The Latest!

Latest Update – January 13, 2025

The intersection of Main Street/S. Winooski is  closed.