Main Street Project Update, May 2, 2025

Construction Update
The intersection of Main/Church is now closed while the contractor replaces the water mains and installs sewer services.
Sewer work at the Main/Union intersection is complete. Surface restoration and paving are complete.
Water main replacement and temporary water main work will continue through May.
Excavation of the roadway subbase along Main St. between Pine and St. Paul is scheduled to begin Wednesday, 5/7.
Please see the parking and traffic sections below for more information on impacts.
NEARBY PROJECT INFORMATION
CHAMPLAIN PARKWAY TRAFFIC HIGHLIGHTS:
Main/Pine Intersection:
Closed 24/7 to vehicles. Parkway contractor (ECI) to take over work from the Main Street contractor (SDI) mid-week.
King/Pine Intersection:
Lane reductions and alternating one-way traffic at the intersection.
Pine St: Main St to King St:
Lane shifts and pedestrian detours will be in effect. Restricted to local vehicle traffic only. Block accessible via King St only.
As construction on the next phase of the Parkway project nears, please visit http://champlainparkway.com/
for more information on construction timelines, traffic impacts and more.
Click HERE to sign up to receive project updates.

Traffic Update
Where is Construction Occuring?
Main/Pine intersection:
Closed 24/7 to vehicles. Bike/Ped access will be maintained for at least 3 legs of the intersection. Parkway contractor (ECI) to take over work from the Main Street contractor (SDI) mid-week.
Main St:
Church St intersection to S. Winooski Ave is fully closed
to vehicle traffic.
Main/S. Winooski intersection:
Open to North/South/East vehicle traffic.
Main/S. Union intersection:
Fully reopened to traffic flow today.
Timeframes for closures are subject to change. Updates will be provided as frequently as possible.
Your understanding and patience are appreciated.
See the map above for street and parking accessibility, construction work locations and detours.
Parking Update
Where can I park?
Don’t Get Stuck in the Mud
Come to Burlington!
This mud season, it’s easier than ever to rediscover downtown Burlington! From cozy cafes to world-class cuisine and unique local shops, there’s a lot to love – and now, it’s easier than ever to park and explore:
FREE 2 Hours on-street parking thru Parkmobile Wednesdays & Thursdays 4/16 – 5/8
FREE 2 Hours at the Downtown Garage Monday – Saturday
FREE parking at meters & City garages on Sundays
This mid-week promo is brought to you by Water Resources.
Shop local, come on downtown!
Available Lots/Garages:
Courthouse Plaza Garage, S. Winooski Ave entrance, city rates ($1.50/hr)
Main/Winooski lot accessed via S .Winooski Ave.
Lower portion only.
On street parking is available except where a meter bag or
‘No Parking’ sign is present.

Nearby Project Alerts
For information on nearby projects, click below to go to the
DPW Construction Portal
For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/
Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts