Sewer work in the intersection of Church and Main will continue. This work will slowly begin to progress east along Main Street next week.
Construction of the new permanent water main on Main Street between Pine and Church is underway. This work is complete near the Main and Pine St. intersection and is continuing east to the Main and St. Paul Street intersection.
Please see the parking and traffic sections below for more information on impacts.
Traffic Update
New 20 MPH Downtown Speed Limit
20 is plenty for Downtown Burlington! Slow down and save lives. Learn more about this change at burlingtonvt.gov/20isplenty
The intersections of Main/St. Paul and Main/Church are
now closed.
All vehicular access on Main Street between St. Paul and Church is restricted.
Church Street from King to Main Street remains closed.
Pedestrian traffic will be maintained around work zones. Follow designated pedestrian signage.
Pedestrian traffic will be maintained around work zones. Follow designated pedestrian signage.
See the map below for construction work locations and detours.
For more information on current construction work locations,
detour, and pedestrian impacts for multiple DPW large construction project impacts within the City, click on the map image below.
Parking Update
Additional public parking is available at the Courthouse Plaza garage
Reduced parking is available on Main Street between Pine and St. Paul Street. No parking is available on Main between St. Paul and Church while both intersections are closed.
Parking directly north/south of the active work zone at the St. Paul Street intersection will be impacted.
Parking at the Courthouse Plaza Garage (South Winooski Ave. entrance only) continues to be available at the City rate of $1.50/hour and space is still highly available.
City rates are only available on the level that is accessed from the South Winooski Ave. entrance.
Some public parking has been restored on the lot located at the corner of Main St. and S. Winooski Ave.
Parking directly in and adjacent to work zones will be impacted, please obey on-street parking signage.
There will be no parking on Main between Pine and Church once the St Paul/Main intersection closes.
Limited on-street parking exists on Main Street between Pine and S Winooski. Please do not park in areas that have meter bags or are coned off.
Please follow signage for access to local businesses and
alternate business parking.
Explore the City of Burlington’s interactive parking map.
Nearby Project Alerts
Church Street Marketplace Construction
Work to repair and replace the Globe on the Church Street Marketplace between Main and College streets is underway.
This work is anticipated to finish by next week.
For information on nearby projects, click below to go to the
DPW Construction Portal
For information on the Champlain Parkway and traffic impacts, click below http://champlainparkway.com/
Sign up for VT-Alert to receive major alerts about work in Burlington
Sign up for VT Alerts