Work continues along Main Street between S. Winooski Ave and S. Union Street. Water service interruptions are scheduled on 2/25 for some properties on this block.
Sewer work on Church Street between Maple and King has been completed for now. The intersection of King and Church will remain closed for several more weeks while the contractor continues excavation for the ravine sewer. Sewer work along King St. to the east of the intersection has begun.
The Main Street/St. Paul Street and Maple Street/Church Street intersections remain closed, however Main Street will be fully reopened at the intersection by the end of the day Friday for the eclipse weekend.
The intersection of Pine and Main is scheduled to reopen on Tuesday, 4/2. Once reopened, the intersection of St. Paul and Main will be closed until further notice.
Intersections of Main Street and Pine Street and Maple Street/Church Street remain closed. An additional 85 parking spaces are available at the Courthouse Plaza parking garage on S. Winooski Ave.
Work continues on the intersection of Pine and Main, and the intersection of Church and Maple. An additional 85 parking spaces have been opened at the Capitol Plaza parking garage for the city rate of $1.50/hr.
The Pine/Main and Church/Maple intersections remain closed for sewer work. A total of 85 parking spaces have been made available to the public at City rates at the Capital Plaza parking garage.
Main Street between S. Winooski Ave. and S. Union St. is scheduled to reopen to through traffic by Monday, 3/4. The intersections of Pine/Main and Church/Maple are scheduled to close after Main Street has reopened.
Work continues along Main Street. Some property owners will experience service disruptions, and have been notified. A neighborhood meeting is scheduled for 2/15.
Construction is on schedule to begin on Monday, 2/5. Some Main Street properties will experience a service interruption. Affected properties have been notified. A neighborhood informational meeting is scheduled for 2/15.